Project Date: February 2019
Client: BG&E
Project Type: Civil & Infrastructure
Location: Perth, WA
Categories: Detailed bridge design
Project Description:
Design & Analysis developed the detailed design for Bridge 1883 for the Leach Welshpool Alliance The two-span bridge has a total length of approximately 90m and will be constructed to accommodate a horizontal curve in the road alignment. It will use 2.1m deep Tee-Roff beams supported on Mechanically Stabilised Earth (MSE) abutments and central blade piers on bad foundations.
Project Scope:
- Detailed headwalls and wing wall design
Outcome:
Design &Analysis collaborated closely with the Alliance team in the development of the design which was developed to MRWA and contractual requirements under the SWTC.